Dwarka Expressway Route Map, Status Update & Latest News

Dwarka Expressway project update, Work completion status, Interchange, Speed limit, India’s first Urban Expressway, IICC Dwarka

IICC Dwarka Expressway

PM Narendra Modi will inaugurate Dwarka Expressway today. Haryana Section of dwarka expressway is fully completed. A little work on Delhi section is left. Part of Delhi section which is completed might be opened as well.

Dwarka Expressway Project Overview

Dwarka Expressway is the India’s first Urban Expressway which is being constructed by National Highways Authority of India (NHAI) under Bharatmala Pariyojana. The project was undertaken to take the traffic load from existing Delhi Jaipur Highway within Gurgaon. With the completion of this expressway residents of Dwarka, New Gurgaon and Najafgarh will get traffic free and smooth connectivity from Airport and south Delhi.

Dwarka Expressway Route map, Length and Construction cost

Lenth of the Dwarka Expressway is around 30 Kilometres and the construction cost for the expressway is around 9500 crores. This will be first Urban Expressway of India which will have 3.6 KM long 8 lane shallow tunnel. Expressway will start at Shiv Murti on existing Delhi Gurgaon highway with multi level interchange facility. It will pass through Existing Urban Extension Road II (UERII) till Bharthal Chowk and will take left turn from there alongside IICC India, from here it will cross Delhi Haryana Border and will run through new Gurgaon area. Expressway will have its end point on Delhi Jaipur Highway near kherki Daula toll plaza

Dwarka Expressway Packages and Length

Package 1 Shiv Murti to Bijwasan (5.3 Km)

Package 2 Bijwasan Underpass to Delhi Haryana Border (4.2Km)

Package 3 Delhi/Haryana border to Basai Railway over bridge (10.2Km)

Package 4 Basai Railway over bridge to Kherki Daula (9.8Km)

Dwarka Expressway Project Progress

Dwarka Expressway Package 1

This package starts near Shiv Murti on Delhi Gurgaon expressway near Indra Gandhi Airport. At Shiv Murti it will have multi level interchange facility for traffic. Traffic will move right for dwarka expressway from shiv murti from there 8 lane shallow tunnel will start. Tunnel will end near Bijwasan Underpass and package 1 will end here.

J Kumar InfraProjects is constructing Package 1 of Dwarka Expressway

Dwarka Expressway Package 1 work completion status

Work on Shiv Murti interchange has started last month and the completion for interchange has been targeted under 90 days. 8 Lane shallow tunnel completed and work of concrete pavement is undergoing inside the tunnel.

Traffic will run above tunnel as well. There will be facility for traffic movement on old Delhi Gurgaon road.

Shiv Murti Interchange :

At Shiv Murti 8 Lanes will be there for the movement of Delhi Gurgaon Traffic.

A 2 Lane bridge will be constructed for traffic towards Dwarka Expressway, Urban Extension Road.

Service Lane for the traffic from Delhi side to Vasant Kunj

Tunnel from Nelson Mandela Road to Dwarka Expressway

Tunnel from Dwarka Expressway to Nelson Mandela Road

Tunnel from Gurgaon side to Nelson Mandela road in Vasant Kunj.

Dwarka Expressway Package 2

This package will start from Bijwasan Underpass to Delhi/Haryana Border. This package will have a interchange at Bharthal Chowk to facilitate the smooth traffic movement towards Dwarka sector 21, Urban Extension Road II (UERII), IICC centre and New Gurgaon.

A flyover has been specially constructed for the smooth traffic movement of the traffic towards exhibition centre.

This phase will have a 32 lane toll plazas just before the Border.

Dwarka Expressway Package 2 work completion status

Interchange At Bharthal Chowk is completed. Some work of blacktop is left. U turn for exhibition centre has been completed.

Work of toll plaza has not started till now.

J Kumar infraprojects is constructing Package 2 of Dwarka Expressway

Dwarka Expressway package 3

Package 3 of Dwarka Expressway will start from Delhi/Haryana Border. At this point elevated expressway of 8 lane will start and will end at Basai Rail over Bridge. Length of the package 3 will be of 10.2 Km in which 8.5 Km Elevated Flyover is constructed. Already constructed Basai flyover will be added with some new lanes to extend it.

In this package Service flyover and Underpass are constructed along Major interchanges.

  • Underpass for Najafgarh Gurgaon Bajghera road
  • Service Flyover for Sector 106 road
  • Daulatabad Chowk crossing
  • Underpass for Delhi Public School Dwarka Expressway
  • Dhanwapura village Underpass

Dwarka Expressway Package 3 Work Completion status

Elevated Road is constructed and Blacktop of the flyover is in progress.

Portion of flyover work is left over Bajghera road

Service Flyover and Underpass are completed and Electricity poles are installed.

Larson & Toubro(L&T) is constructing this package.

Dwarka Expressway Package 4

Package 4 of Dwarka Expressway starts near Basai Rail over Bridge and will end at kherki Daula on Delhi Jaipur Highway where it will merge with Southern Peripheral Road(SPR). Majority of the Portion of this package is elevated. A trumpet Interchange is constructed for the moment of traffic for IMT Manesar, sector 88, sector 84. At Trumpet Interchange it will connect with Central Periphery Road. Package will have Clover leaf interchange at National Highway 44.

Dwarka Expressway Package 4 work completion status

Majority of the portion of this package is complete. Underpass are completed.

Cloverleaf Interchange work is going near Kherki Daula where expressway will connect to Southern Peripheral Road.

From package 4 a new expressway for Delhi and Jaipur will be started which will be known as Delhi Jaipur Super Expressway.

Larson & Toubro(L&T) is constructing this package

Dwarka Expressway structures

  • 20 Bridge Flyovers
  • 2 Railway over bridge
  • 11 Vehicle Underpass
  • 20 Pedestrian Underpass
  • 2.5 Metres in width Cycle Corridors

Acces Controlled smart expressway with CCTV security.

Speed Limit at Dwarka Expressway will be 80-100 Km/hr.

What is the date of Completion of Dwarka Expressway ?

Dwarka Expressway will be completed in July 2023.

Is Dwarka Expressway in Delhi or Gurgaon ?

Package 1 and Package 2 of Dwarka Expressway are in Delhi. Package 3 and package 4 are in Gurgaon.

What is the benefit of Dwarka Expressway ?

Resident of new Gurgaon will get seamless connectivity with the construction of Dwarka Expressway. Sector of Dwarka will be helped. People of Vasant Kunj can easily travel towards gurgaon and Najafgarh.

What is the status of Dwarka Expressway ?

85-90 percent of work is completed. Expressway will be ready in July 2023.

Disclaimer : The views expressed above are for informational purposes only based on reports and news articles. ExpresswayInfo does not guarantee the accuracy, completeness, or reliability of the information and shall not be held responsible for any action taken based on the published information.